Thursday 18 December 2014
Clermont-Ferrand Airport – Runway maintenance
4th quarter 2014 – The Technical Department at Clermont-Ferrand Auvergne Airport (Vinci Airport) carried out maintenance work on its runway 08/26 (3015 m x 45 m) in just four nights:
- Water jet rubber removal of threshold 26
- Regulatory skidding control measurements
- Bridging longitudinal and transverse cracks
- Caulking cable channels from the former lighting system
All tasks were carried out with optimum scheduling in a very short timeframe (4 nights – 11pm-5am) thanks to the resources mobilised and NEOVIA teams’ experience in airport works. Clermont-Ferrand Auvergne Airport is now able to bring the markings on runway 08/26 into line with standards.